Project: "CONSTRUCTION OF AEOLIKI WIND PARK IN THE POSITION OF ERESSOU FOURKA MOUNTAIN"
Place: MUNICIPALITY OF VERIAS PREFECTURE OF IMATHIAS, GREECE
Budget: 41.970.000,00€
Contractor: TERNA ENERGY S.A.
Subcontractor: PYRAMIS SA
Value of executed works: 1.200.000,00€
Place: MUNICIPALITY OF VERIAS PREFECTURE OF IMATHIAS, GREECE
Budget: 41.970.000,00€
Contractor: TERNA ENERGY S.A.
Subcontractor: PYRAMIS SA
Value of executed works: 1.200.000,00€
Project Overview
The project concerns the installation of a wind farm consisting of 18 wind turbines with a power of 2 MW each, totaling 36 MW, with a total area of approximately 3.500 km2.
For this purpose the following works were performed:
- New internal road network was established
- The construction of the platforms for the construction of the wind turbines
- The construction of the foundations
- The control building
- The installation of the underground cable by the opening of the required ditch for the installation and rebuilding with related pavement work