Mines Projects

Mines Projects

PYRAMIS S.A. has extensive experience in Mining projects since it has undertaken and executed a large number of these for the last 18 years, for PPC SA. PYRAMIS S.A. has worked in the Mines of Amynteon, Mavropigi, Meliti, Kardia and others. The total budget of the executed mining works amounts to 97.121.088,63 €.

Major Projects

  • Moving of 700.000 Μ3 earh materials from the external Deposit aea of the Coal Mine area - South Field
    OVERALL VALUE: 993.660,73€
  • Moving of 1,73 x 106 Μ3 of lignite from the east slopes of Coal Mine- Amindaio field
    OVERALL VALUE: 130.5756,03€
  • Moving of 530.000 Μ3 of lignite from the ODP3 of Coal Mine- Mavropigi field
    OVERALL VALUE: 493.469,21€
  • Moving of 150.000 Μ3 of lignite from the ODP3 of Coal Mine- Mavropigi field
    OVERALL VALUE: 145.299,84€
  • Moving of 19,7Χ106 Μ3 of earth materials and lignite from the ODP3 of Coal Mine- Mavropigi field
    OVERALL VALUE: 16.752.998,59€
  • Formation of 3,3Χ106 Μ3 Deposited materials for shaping the plateu of the final deviation of the Railway Line, the relocation of the Railway line of the old National Road Kozani-Ptolemaida and the new sute road in the area of the external deposits of Coal Mine- Kardia field
    OVERALL VALUE: 4.843.611,63€
  • Moving 12,0X106 M3 earth materials and lignite in the area ODP3 of Coal Mine Mavropigi
    OVERALL VALUE: 14.796.592,53€
  • Moving 9,0X106 M3 hard and semi-hard materials from the sections of sector 6 of Coal MineSouth field, moving 0,65X106 M3 sand gravel materials for the infrastructure-Support and moving 0,13X106 M3 clay materials from the plateus of the coal mine of south field
    OVERALL VALUE: 17.762.675,63€
  • Moving 3,0 x 106 M3 of lignite from the slopes of sector 6 of coal mine of south field
    OVERALL VALUE: 2.843.989,18€
  • Moving 5,5 x 106 M3 of lignite from the degraded area of sector 6 of coal mine of south field
    OVERALL VALUE: 4.107.533,81€
  • Moving 10,0 x 106 M3 of lignite from the terminals of the sections 1 and 2 of sector 7 of coal mine of south field
    OVERALL VALUE: 12.575.190,84€
  • Excavation-Loading-Transport-Deposit and Grading of 3,6 x 106 tons of solid sub-products from the Power Plant Station Meliti
    OVERALL VALUE: 2.223.740,00€
  • Moving of 5,4 × 106 Μ3 of overburden from the pre-section of coal mine Mavropigi
    OVERALL VALUE: 4.348.900,00€
  • Excavation-Loading-Transport-Deposit and Grading of 3,65 x 106 M3 of earth materials for the formation of the slopes in the peak of the landslide area in coal mine Amindaio
    OVERALL VALUE: 2.701.000,00€
  • Moving 9,88 × 106 Μ3 of overburdwn (schist) from the SW slopes and supporting works of coal mine Mavropigi
    OVERALL VALUE: 1.0473.000,00€